| We need $40million for new Jinja Bridge, Nasasira |
|
“We are already talking with the
Japanese [government] and African Development Bank and hope to raise this money
[$40 million] and start constructing the new bridge,” Mr Nasasira said on
Wednesday. He said Ministry of Finance has consistently
failed to avail money for putting up a
new overpass on the Jinja route that provides landlocked
In
1997, Sir Alexander Gibb & Partners consulting engineers then
executing remedial works on Owen Falls
dam formally wrote to Ministry of Works officials indicating that
the developing cracks on the Owen Falls bridge at the time were “very serious,”
making it usable for only 5-10
additional years.
To
allay growing public anxiety, minister Nasasira said UK
divers, Associated Consulting engineers and Mott MacDonald’s – all foreign
consultants carried separate studies between 2003 and 2006, concluding the Owen
Falls dam bridge could still work with
remedial repairs. Following the recommendations, the government did patch-work
on the bridge to reinforce splitting pre-cast underneath slabs using asphalt,
refurbished the joints and placed humps at the bridge approach to limit drive
speed below 30 kilometers per hour.
|